NOAB Project 0991

Overview

This project provided for the replacement of 17 aircraft loading bridges. It was divided into two phases: Base Bid, which replaced 10 bridges and Bid Option #1, which replaced 7 bridges.  After the completion of the original Base Bid, Bid Option #1 and all of the change orders, the New Orleans Aviation Board (NOAB) approved Bid Option #2. Bid Option #2 encompasses the addition of 6 passenger boarding bridges required for the Concourse "D expansion.
 
Project Personnel

Construction Schedule





Project Manager

Dale Trahan, ART

  Notice to Proceed

2-4-08

Architect/Engineer

Parsons Aviation Louisiana (PAL)

  Project Duration (Days)

270

Contractor PM

Manuel Torres

  Completion Date

10-30-08

Contractor

Thyssen-Krupp

  Delay/Extension (Days)

937

      Revised Completion Date

5-25-11*

Project Budget








Costs

Percentage
Construction

$11,537,767

     
Change Orders

$(342,538)

     
Design

$0

     
Other

$0




PM/CM

$353,877

   3.1%
Total

$11,549,106




 
Project Status
  • Construction complete.  Closeout in progress.

 