Capital Improvements
> Projects Completed
> Airfield Rescue and Fire Fighting (ARFF) Facility
|
<< Return
|
Airfield Rescue and Fire Fighting (ARFF) Facility
|
NOAB Project
0978
Overview
This project provides a modern ARFF Station just to the west of
the existing facility which is both antiquated and located on a constrained site
that didn't allow for expansion. The project also included the demolition of the
DHL hangar and apron.
Project
Personnel |
|
|
Construction
Schedule |
|
|
|
|
|
|
Project Manager |
Jay Scalise, ART |
|
Notice to Proceed |
10-23-09 |
Architect/Engineer |
Hegedus-ECM
Architects |
|
Project Duration (Days) |
365 |
Contractor PM |
Steven Mendoza |
|
Completion Date |
10-22-10 |
Contractor |
Satterfiled & Pontikes
Construction , LLC |
|
Delay/Extension (Days) |
325 |
|
|
|
Revised Completion Date |
9-12-11 |
Project
Budget |
|
|
|
|
Costs |
|
|
Percentage |
|
Construction |
$9,913,000 |
|
|
|
Change
Order |
$396,000 |
|
4.0% |
|
Design |
$1,084,177 |
|
10.9% |
|
Other |
$376,367 |
| 3.8% |
|
PM/CM |
$870,142 |
| 8.8% |
|
Total |
$12,639,686 |
|
|
|
Project Status
-
Construction completed 6/2013, project closeout scheduled for 7/2013.
|
|
|
|
|
|