Exterior Terminal Improvements: Phase 2

NOAB Project 1067

 
Overview
This project provides for the modernization of the exterior features of the Terminal building. On the upper level, the curtain wall facade will also be replaced with windows and new entrances. Expansion joints along the Terminal facade will be replaced. The inner and outer roadway curbs will be expanded by 3 ft on both levels and roadway lane widths will be narrowed accordingly. This project was bid with the Interior Terminal Improvements Phase 3 project (NOAB Project #1065) and has been coordinated to mitigate passenger and tenant impacts.
 
Project Personnel

Construction Schedule





Project Manager

Harvey Goldstein, ART

  Notice to Proceed

8-16-10

Architect/Engineer

Sizeler/Thompson/Brown

  Project Duration (Days)

360

Contractor PM

Steven Sentiles

  Completion Date

8-10-11

Contractor

Gibbs Construction

  Delay/Extension (Days)

143

      Revised Completion Date

4/2013

Project Budget



Costs

Percentage
Construction

$5,242,845

     
Change Orders

$133,603

  2.5%  
Design

$761,400

  14.5%  
Other

$175,000


3.3%
PM/CM

$371,793


7.1%
Total

$6,684,641

   
 

Project Status
  • Construction closeout 4/2013 with project closeout to be completed by 5/2013
  •  

 