Capital Improvements
> Projects Completed
> North Perimeter Road Improvements
|
<< Return
|
North Perimeter Road Improvements
|
NOAB Project 1083 Overview
This
project provides for the rehabilitation and realignment of the existing
North Perimeter Roadway into a new, wider road that is easier to
navigate. Also included in this project is the re-contouring of nearby
drainage ways. The project was originally combined with the Runway 6-24 Conversion Project (NOAB Project #1086) , but was split apart due to funding issues. Project Personnel |
|
| Construction Schedule |
|
|
|
|
|
| Project Manager | Jay Scalise, ART |
| Notice to Proceed | 01-18-11 | Architect/Engineer | Lambert Engineers, LLC |
| Project Duration (Days) | 270 | Contractor PM | John Rodriguez |
| Completion Date | 10-18-11 | Contractor | Gibbs & Register Inc. |
| Delay/Extension (Days) | 55 |
|
|
| Revised Completion Date | 11-09-11 | Project Budget |
|
|
|
|
|
|
|
|
| Costs |
|
| Percentages |
| Construction | $2,964,313 |
|
|
| Change Orders | $147,511 |
| 4.9% |
| Design | $371,709 |
| 15.5% |
| Other | $220,000 |
| 7.4% |
| PM/CM | $392,051 |
| 13.2% |
| Total | $4,095,584 |
|
|
|
Project Status The rehabilitation and realignment of the existing North Perimeter Road to a new wider roadway that is easier to navigate. Construction, Change Order, Design, and Other costs are costs approved by the Board. The PM/CM cost is actual spending as of November 2011. Other costs include Resident Inspection and Materials Testing services.
|
|
|
|
|