Phase 4 (A) Improvements

NOAB Project 1100


Overview

This project includes the reconfiguration of the security checkpoint screening lanes at Concourse D to increase the ingress and egress capacity at the checkpoint. The renovation work will include carpet replacement, painting, speaker replacement, installation of additional lighting, new laptop counters, and reupholstering of all concourse seating. Additional items under this project include replacement of all signage throughout the airport, rehabilitation of the Concourse C tug tunnel, and cleaning of canopies in between the parking garage and terminal.
 
Project Personnel

Construction Schedule





Project Manager

Kevin Spruell, NOAB


Notice to Proceed

TBD

Architect/Engineer

Sizeler/Perez/URS


Project Duration (Days)

150

Contractor PM

TBD


Completion Date

TBD

Contractor

TBD


Delay/Extension (Days)

0




Revised Completion Date


Project Budget








Costs

Percentage
Construction

$3,800,000




Change Orders

$0




Design

$200,000


 
Other

$170,000




PM/CM

In-house




Total

$4,170,000




 
Project Status
  • Construction completed 6/2013, project closeout scheduled for 7/2013.

 