Louis Armstrong New Orleans International Airport



Capital improvements
New Airfield Lighting Vault

NOAB Project 1088

 
Overview

This project provides a new airfield lighting vault on the north side of the airfield to the east of the existing General Aviation apron area. .
 
Project Personnel

Construction Schedule





Project Manager

Dale Trahan, ART

  Notice to Proceed

1-31-11

Architect/Engineer

MCA

  Project Duration (Days)

270

Contractor PM

Jamie Franks

  Completion Date

11-27-11

Contractor

Ronald Franks Construction, LLC

  Delay/Extension (Days)

57

      Revised Completion Date

6-20-12

Project Budget








Costs
  Percentage
Construction

$4,490,000

     
Change Orders

$246,523

  5.5%

 

Design

$422,872

  9.4%  
Other

$225,000


5.0%
PM/CM

$377,620


8.4%
Total

$5,762,015

   
 
Project Status
 
  • New airfield lighting vault on the north side of the airfield, to the east of the General Aviation apron area.
  • Construction, Change Order, Design, and Other costs are costs approved by the Board.
  • The PM/CM cost is the total budgeted amount for the entire project.
  • Other costs include Resident Inspection and Materials Testing services.
  •