Louis Armstrong New Orleans International Airport



Capital improvements
Part 1542 Security System

NOAB Project 0963


Overview

This project provides for the installation of a state-of-the-art access control system that includes a Closed- Circuit Television Network (CCTV), telephone system, computer aided dispatch, Emergency Operations Center and security badge system. Also included in this project is the construction of a communications center (AVCOM) facility and data center.
 
Project Personnel

Construction Schedule





Project Manager

Harvey Goldstein, ART

  Notice to Proceed

10-18-06

Architect/Engineer

NY & Associates

  Project Duration (Days)

730

Contractor PM

Walt Prusak

  Completion Date

10-16-08

Contractor

Johnson Controls

  Delay/Extension (Days)

760

      Revised Completion Date

11-15-10

Project Budget








Soft Costs

$9,752,250

   FAA Funding  
Construction and Other Costs

$23,299,359

   AIP Grants  $13,280,929
Total Project Cost

$33,051,609

     
Total Expenditures (to date)

$28,791,917

   
 
Project Status
  • Johnson controls is wrapping up the project per the original scope and additional 16 change orders
  • Construction of the AVCOM, Network Operations Center, and Emergency Operations Center is 98% complete, with only minor work remaining.
  • The software installation and programming associated with this project along with the integration of the systems is complete.
  • Currently, though many of the components of the system have been installed, only the security Badge System, wireless and network are operational.
  • The remaining change order items include: The fire alarm feature for AVCOM, the checkpoint shutdown and additional security features.