Louis Armstrong New Orleans International Airport



Capital improvements
Consolidated Rent-A-Car (CONRAC) Garage

NOAB Project 1064

Overview

This project provides for the construction of a customer service building, a ready-return parking garage, new utility building and associated service areas for the rental car companies to maintain their vehicles. The facility will also include concessions and will be connected to the Terminal via covered walkways.
 
You can view progress of this project by watching our Construciton Cam -> Consolidated Rent-A-Car Garage Project
 
Project Personnel

Construction Schedule





Project Managers
Tim Murray , ART 
  Notice to Proceed

7-6-10

Architect/Engineer

Coover-Clark & Associates

  Original Project Duration (Days)

730

Contractor PM

Dick Pirkle

  Completion Date

 2-21-13

Contractor

Satterfield & Pontikes Construction

  Delay/Extension (Days)

231

      Revised Completion Date
2-21-13
Project Budget








Costs

Percentage
Construction

$58,475,000

 
 
Change Order

$21,434,230

   36.6%  
Design

$8,810,666

   15.1%  
Other

$1,025,000


   1.8%
PM/CM

$3,308,314


   5.6%
Total

$93,053,210

   
 
Project Status
  • Construction expected to be completed 7/2013, project closeout scheduled for 8/2013.