Louis Armstrong New Orleans International Airport



Capital improvements
Interior Terminal Improvements Phase 1 (Restrooms)

NOAB Project 1020


Overview

This project provides for the complete rehabilitation of 12 restrooms along with minor renovations to an additional 9 restrooms throughout the terminal and all concourses. Work has been phased with other planned/ current interior construction work in the Terminal to minimize impacts to passengers. (This project was originally bid in 2009 but was rebid in 2010).
 
Project Personnel

Construction Schedule





Project Manager

Kendrick Hunt, ART

  Notice to Proceed

03-04-10

Architect/Engineer

Murray Architects

  Project Duration (Days)

365

Contractor PM

Kent DeMara

  Completion Date

03-03-11

Contractor

Gibbs Construction

  Delay/Extension (Days)

192

      Revised Completion Date

4/2013


Project Budget



Costs

Percentage
Construction

$4,436,000

     
Change Orders

$1,090,929

  24.5%  
Design

$570,598

  12.9%  
Other

$247,500


  4.5%
PM/CM

$554,987


11.8%
Total

$7,501,772

   
 
Project Status
  • $8.8M. Construction complete, Final closeout 4/2013.