Louis Armstrong New Orleans International Airport



Capital improvements
Terminal Apron Rehabilitation: Phase 2 (Alternate #1)

NOAB Project 1096


Overview

This project provides for the replacement of portions of the air carrier apron surrounding Concourse "B specifically the pavement between Concourse "B and "C including the aircraft gates. Construction of this work has been phased for minimal impact to airline operations.
Project Personnel

Construction Schedule





Project Manager

Tim Murray, ART

  Notice to Proceed

5/2013

Architect/Engineer

Evans-Graves Engineers

  Project Duration (Days)
Contractor PM

Allen Mikles

  Completion Date
Contractor

J.B. James

  Delay/Extension (Days)
      Revised Completion Date
Project Budget



Costs

Percentage
Construction

$36,400,261

     
Change Orders

$0

     
Design

$2,677,142

   7.4%  
Other

$550,000


1.5%
PM/CM

$920,797

   2.5%
Total

$40,548,201




 
Project Status
  • Terminal Apron Rehab Phase II FAA approval to proceed with using remaining grant. Construction to begin 5/2013