COVID-19 Updates: Click here for updates to airport operations.
Local Weather
Select Page

Extension of Taxiway Golf and Taxiway Bravo Project

Contractor: Barriere Construction Co., LLC

 

Cost: $50,783,229 NTE

 

Start Date: November 11, 2020

 

End Date: October 28, 2021

 

Project Status: Contract signed by all parties.

Pre-construction meeting scheduled for Wednesday, October 21,2020.

 

Current Activity: Contractor started badging process, ordered required software, and began process of setting up construction trailer.

 

Project Description: The primary purpose of the project is to construct and extend Taxiway Golf (G) to the west of its current location. With the opening of the new Terminal, north of Runway 11/29, Taxiway G needs to be extended to better accommodate the traffic that will use Runway 11-29, specifically the 29 Approach.
 
The extension will be an additional 1500 feet from the existing west end of Taxiway G and will connect Taxiway G with the Runway 11 end. In addition, Taxiway Bravo will be built out from its current stub out from Runway 11-29 and tie into Taxiway G.
 
The project will also include installation of lighting and signage for all new pavements.